As of October 2026, data center developers in the United States had announced plans for more than 100 behind-the-meter gas power plants, according to data from market intelligence firm Cleanview. The projects represent more than 115 gigawatts of planned capacity—more than twice California’s peak electricity demand. Although only a few are operating or under construction, the trend could influence the power grid and climate for decades.
Most of the announcements were made after the beginning of 2025, as developers sought electricity for the rapid expansion of artificial intelligence infrastructure. Building dedicated power plants is generally more expensive than connecting a facility to the grid, but the need to bring data centers online quickly has made developers willing to pay a substantial premium.
“Right now, the biggest motivator for on-site power from data centers is speed,” said Musfika Misi, an associate at energy consultancy BloombergNEF.
Why data centers are building their own power
When a developer proposes a new industrial facility that requires large amounts of electricity, it must request a grid connection from the local utility or regional grid operator. That begins a multiyear process in which grid planners assess what must be built to supply the facility safely without compromising reliability.
The required upgrades may include new transmission or distribution lines and larger transformers, and the developer may be required to pay for some or all of that work. Rather than wait for the process to finish, developers can build power plants on their own sites.
These facilities are known as “behind-the-meter” because they are located on the customer’s side of the utility meter. They supply electricity directly to the building instead of relying entirely on power delivered through the grid.
“The shift to off-grid gas in data center developers’ power strategies raises some important questions about how data centers will be powered in the future,” said Brendan Pierpont, director of power at the think tank Energy Innovation.
A temporary solution—or a long-term commitment?
Behind-the-meter generation does not necessarily mean a facility will remain completely disconnected from the grid. Some developers may use on-site plants as a temporary measure, later connecting to the grid and retaining the plants primarily as backup sources.
“It’s really just a very expensive way to close a gap in the schedule, which is probably five to seven years until these data centers can connect to the grid,” Pierpont said.
However, even a short-term plan to use gas can create long-term consequences. Once operators have invested in fossil-fuel infrastructure, they may decide to keep the plants running for longer than initially intended.
“While data centers say this is a grid bridge solution, the real risk is that it could be used much longer, and that would lead to fossil fuel lock-in,” Misi said.
Source: www.technologyreview.com